City Council · Thursday, February 27, 2025 · 6:30 PM
Regular Council Meeting
Summary
The Freeport City Council met on February 27, 2025, to discuss routine city business and address a council vacancy. The council approved several infrastructure projects including resurfacing Azalea Drive for $18,300, installing a new crosswalk north of Stowaway Storage, and two for the Community Center totaling $62,500. They also approved Change Order #7 for the wastewater treatment plant expansion ($101,961.03, subject to USDA approval), the final phase of the Hammock Bay residential development (162 single-family homes), and events including the Fourth of July parade and Springfest Eggstravaganza. The Planning Director noted concerns about illegal off-premise signage in the city and proposed a quarterly public awareness campaign. Most significantly, following Councilman Day's resignation on February 24, the council appointed Heather Ray Hurst (Chairwoman of the Planning Board) to fill the vacant council seat for the remainder of his term, with TJ Kent appointed to the Planning Board vacancy that resulted.
Why it matters
The council's approval of infrastructure improvements and the Hammock Bay final phase will continue development in Freeport, while the council vacancy appointment ensures full council representation. Residents should be aware that the city is enforcing signage regulations and promoting legitimate business advertising through the new feature program.
What happened
Development & zoning4 items
Hammock Bay 5 Approval
Passed 4–0 · unanimousPlanning Director presented the final neighborhood of Hammock Bay development, a 43.95-acre residential project with 162 single-family lots (previously approved in September 2024). The Planning and Development Review Board recommended approval with conditions on February 5. The project includes several (reduced lot widths, , and pool placement) consistent with other Hammock Bay phases. Conditions include disclosure of adjacent bee farm, installation of a 6-foot privacy fence along the bee farm boundary, and a 25-foot native vegetation buffer for residents on Powerline Road. 2025-01.
Where: East side of Bay Loop East, 200 feet south of Hansen Road, extending almost to Powerline Road
Part of project: Hammock Bay PDP 5
Community Center #1 (Fiber Optic and Irrigation)
Passed 4–0 · unanimousPlanning Director presented a for additional conduit for fiber optic cable, irrigation, and labor at the Community Center project.
- $24,000.00 · Change order for additional conduit for fiber optic cable, irrigation, and labor at Community Center
Part of project: Community Center
Community Center #2 (Planning Building Parking Area Repairs)
Passed 4–0 · unanimousPlanning Director presented a for repairs to the Planning and Zoning parking area, including redoing sidewalk, leveling asphalt, and fixing sewer service to prevent future flooding.
- $38,500.00 · Change order for repairs and remodel of Planning and Zoning parking area
Planning and Zoning Building Repairs Bid Authorization
Passed 4–0 · unanimousPlanning Director requested authorization to put the Planning and Zoning building (the oldest building on the property) out for bid to evaluate needed repairs. The council approved sending it out for bid with a 60-day review period to determine the scope and cost for potential inclusion in the budget.
Roads & infrastructure2 items
Azalea Drive Resurfacing
Passed 4–0 · unanimousCity Manager received a request from Walton County to resurface Azalea Drive. The council approved the cost for materials and striping.
- $18,300.00 · Cost for materials to resurface Azalea Drive and stripe it
Where: Azalea Drive
Crosswalk Installation
Passed 4–0 · unanimousCity Manager announced a new crosswalk to be installed just north of Stowaway Storage in conjunction with the Azalea Drive resurfacing project during Spring Break. Walton County will provide pricing for the signage.
Where: North of Stowaway Storage
Utilities1 item
#7 Expansion
Passed 4–0 · unanimousFinance Director presented #7 for the wastewater treatment plant expansion, specifically for remote access to the blowers. The council approved the change order, which is subject to USDA approval.
- $101,961.03 · Change order for remote access to the blowers at WWTP expansion, subject to USDA approval
Parks2 items
2025 Freeport Freedom Parade (Fourth of July)
Passed 4–0 · unanimousCommunity Outreach Coordinator requested approval for the Fourth of July parade and its route for permitting and signage. The route will be the same as in past years.
Springfest Eggstravaganza Graphics Approval
Passed 4–0 · unanimousCommunity Outreach Coordinator requested approval of graphics for the Springfest Eggstravaganza event. Once approved, the coordinator will post to social media and publicize the event.
Other5 items
Off-Premise Signage Enforcement
Planning Director announced concerns about illegal off-premise signage (wind feather signs, snipe signs) throughout the city . The council agreed to conduct quarterly public service announcements about the prohibition on off-premise signage and to remove non-compliant signs to storage for owner pickup.
Business Feature Program
Planning Director proposed featuring a local business with its logo and information once per month in city communications to build relationships between the city and its businesses. The council approved continuation of this initiative.
Approval
Passed 4–0 · unanimousThe council approved bills, Revenue & Expenditure Reports through January 2025, and Regular Council Meeting Minutes from February 11, 2025 on the .
Council Seat Vacancy - Appointment of Heather Ray Hurst
Passed 4–0 · unanimousCouncilman Day resigned on February 24, creating a council vacancy. The City Attorney explained that the vacancy must be filled by majority vote of the council. Councilwoman King nominated Heather Ray Hurst (Chairwoman of the Planning Board), who was supported by Councilwomen King and Haffner. Councilman Farris nominated TJ Kent. The council voted to appoint Heather Ray Hurst to serve out the remainder of Councilman Day's term. She will be sworn in at the next meeting.
Planning Board Appointment of TJ Kent
Passed 4–0 · unanimousFollowing Heather Ray Hurst's appointment to the council, Councilwoman King nominated TJ Kent to fill the Planning Board vacancy. The council approved the appointment.
Coming up
- Heather Ray Hurst to be sworn in as new council member
- Baseball and Softball opening day at Freeport Sports Complex · March 8
- Planning Board meeting