Construction adding conduit, irrigation, and labor work at the city's Community Center building project.

Key facts

Who is deciding
City of Freeport
Where
Not on the map yet: the documents we have don't give a parcel number or street address.

Timeline

2 items, oldest first. Each links to the meeting and the original documents.

  1. Feb 27, 2025City Council

    Community Center Change Order #1 (Fiber Optic and Irrigation)

    Change order for conduit/fiber/irrigationPassed 4–0 · unanimousUnder construction

    Planning Director presented a for additional conduit for fiber optic cable, irrigation, and labor at the Community Center project.

    Meeting page Agenda (PDF)Minutes (PDF)

  2. Oct 23, 2025City Council

    Change Orders for New Community Center

    Change orders approvedPassed 4–0 · unanimousUnder construction

    Approved two for the Community Center project, primarily related to technology installation in the building.

    Meeting page Agenda (PDF)Minutes (PDF)

Written partly by AI from the documents linked above; check them before relying on a detail · Independent, not an official city site · Source · Privacy · Terms