Board of County Commissioners · Tuesday, January 27, 2026 · 1:00 PM · South Walton Annex BCC Boardroom, 31 Coastal Centre Blvd. Santa Rosa Beach, FL 32459
County Commission
Summary
The Walton County Board of Commissioners met on January 27, 2026, to consider routine business, multiple major development projects, and policy matters. The board approved several items including equipment leases, grant applications for road improvements, and development orders for residential and commercial projects. Key discussions included a $1 million allocation for an Agriculture Center project using beach vending revenue (which failed 2-3), tabling the Eastern Lake Regional Beach Access project, adopting a supporting law enforcement, approving planning software contracts totaling up to $1.01 million, and confirming a 42-townhome development near Commercial Parkway. The board also addressed updates on wireless broadband (Wildstar), beach nourishment, and legislative matters.
Why it matters
The board's approval of multiple major residential and commercial development projects will shape future growth in Walton County, while decisions on the Agriculture Center project and Eastern Lake beach access reflect the board's values regarding community facilities and environmental protection. The technology investments in planning software and broadband expansion will improve county services and infrastructure.
What happened
Development & zoning12 items
South Walton patio shade structures development order agent designation
Passed 5–0 · unanimousApproved on . Agent Affidavit designating Charles Cotton, P.E. to act as agent for development order for patio shade structures at South Walton , 63 South Centre Trail, Santa Rosa Beach, FL 32459.
Where: 63 South Centre Trail, Santa Rosa Beach, FL 32459
Westonwood Ranch Expansion development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order for private congregate care facility on 37.89 acres. Project MAJ25-000043, located at 4384 and 4390 State Highway 20 West, District 1.
Where: 4384 State Highway 20 West; 4390 State Highway 20 West; 11-1S-20-32000-038-0040; 11-1S-20-32000-038-0030
Bay Grove Road Flex Space development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order for 50,625 square-foot commercial building (two one-story buildings under one roof) divided into units for leasing on 5.06 acres. Project MAJ25-000055, located on north side of US Highway 331 South, east of Bay Grove Road, District 1.
Where: US Highway 331 South, East of Bay Grove Road; 03-2S-19-24000-003-0000
Capital Vet Clinic development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order for 20,144 sf main vet building, 10,125 sf flex space, and future 10,075 sf of additional vet clinic space on 6.06 acres. Project MAJ25-000042, located at corner of Coy Burgess Loop and US Highway 331 South, District 3.
Where: Coy Burgess Loop and US Highway 331 South; 15-2N-19-18050-00C-0011; 14-2N-19-18000-003-0010
DW Sitework borrow pit development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order to develop a borrow pit on 11.86 acres. Project MAJ25-000047, located on south side of Highway 90 West, east of Rainbow Road, west of Laird Road, District 3.
Where: Highway 90 West, East of Rainbow Road, west of Laird Road; 19-3N-21-37000-002-0050
Hunters Village development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order for 31 single family lot on 9.67 acres. Project MAJ25-000045, located at 321 Nellie Drive, District 5.
Where: 321 Nellie Drive; 23-2S-20-33170-000-0110
Luxe Apartments development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order for 240-unit apartment complex with clubhouse, pool, and public recreational facilities on 24.47 acres. Project MAJ25-000040, located on north side of U.S. Highway 98 West, east of Veterans Road, west of Old Blue Mountain Road, District 5.
Where: U.S. Highway 98 West, east of Veterans Road and west of Old Blue Mountain Road; 25-2S-20-33190-000-0480; 36-2S-20-33290-000-0330; 0340
Naturewalk Amendment development approval
Passed 5–0 · unanimousApproved on . Acceptance of ALJ recommended order and approval of final order to amend Tract H from multifamily to single-family residential on 1.36 acres. Project MAJ25-000049, located approximately 1 mile east of County Highway 395 South, District 5.
Where: County Highway 395 South; 11-3S-19-25010-000-00H0
EPL Assist Basic services and SwiftGov contract amendment
Passed 5–0 · unanimousApproved. Agreement with Tyler Technologies to purchase EPL Assist Basic services. Additionally, approval given for proposed amendment to SwiftGov contract to extend time period and add three components: AI-Driven Rewrite, AI-Assisted Plan Review, and Customer Service/Case Management/SOP services.
- $40,000.00 · Amount not to exceed for EPL Assist Basic services
- $970,000.00 · Amount not to exceed for SwiftGov contract amendment over three years
Planning audit update
Discussion. CFO Thomason anticipates draft audit by end of week; final audit will be presented at future regular meeting.
Inlet Beach Neighborhood Plan
Passed 5–0 · unanimousContinued to February 26, 2026. to correct scrivener's error in Section 2.2.7 of Inlet Beach Neighborhood Plan. Second and final reading postponed.
Hidden Pines Townhomes development approval
Passed 4–1 · splitApproved. Amended final order for major development order application MAJ23-000018. Approval to develop 42 townhomes and associated infrastructure on 5.79 acres. Project located in District 4 on west side of Goldsby Road, north of Commercial Parkway, south of Rivercrest Circle. Error in initial traffic distribution analysis corrected; proportionate fair share recalculated.
Where: West side of Goldsby Road, north of Commercial Parkway and south of Rivercrest Circle; 25-2S-21-42000-005-0000
Budget & taxes3 items
Expenditure Approval List (EAL)
Passed 5–0 · unanimousApproved on . Total expenditures of $11,410,404.19 across all county funds.
- $11,410,404.19 · Total expenditures approved
Elections voting equipment storage lease renewal
Passed 5–0 · unanimousApproved on . Amendment No. 2 and 2026-2027 option renewal with Ken Mitchem for Supervisor of Elections voting equipment storage space, effective January 11, 2026 through January 10, 2027.
- $700 per month · Monthly storage lease fee
Property and casualty insurance brokerage services solicitation
Passed 5–0 · unanimousApproved on . Request approval to advertise a solicitation for property and casualty insurance brokerage services.
Roads & infrastructure7 items
Chat Holley and US Highway 331 Intersection Improvements funding application
Passed 5–0 · unanimousApproved on . Request approval to apply for funding through Florida Department of Transportation County Incentive Grant Program (CIGP).
CR 1883 Phase 2 and Phase 3 funding applications
Passed 5–0 · unanimousApproved on . Request approval to apply for funding through Florida Department of Transportation Small County Road Assistance Program (SCRAP).
CR 280 Bob Sikes Phase 2 and CR 3280 Phase 1A funding applications
Passed 5–0 · unanimousApproved on . Request approval to apply for funding through Florida Department of Transportation Small County Outreach Program (SCOP).
US Highway 98/Moll Drive Signalization Project contract time extension
Passed 5–0 · unanimousApproved on . No. 1 to Construction Contract No. 24-42 with Murdock Investments, LLC d/b/a Griffin Traffic Signals, increasing contract time by 115 calendar days.
Guardrail Installation and Repair Services contract renewal
Passed 5–0 · unanimousApproved on . Second Option to Renew Contract No. 24-04 with Grading and Bush Hog Services for Guardrail Installation and Repair Services.
Public Works Department Quarterly Report
Passed 5–0 · unanimousApproved. Report for October through December 2025 was accepted.
Road striping assistance to Holmes County
Passed 5–0 · unanimousApproved. Request approval to provide road striping assistance to Holmes County on County Road 179 under existing .
Where: County Road 179
Utilities4 items
Public Safety Communications System site lease agreements
Passed 5–0 · unanimousApproved on . Site lease agreements for Glendale, Argyle, Miramar, Woodlawn, Pleasant Ridge, and Childrens Home tower sites between West Coast Holdings, LLC and Walton County.
Freeport Library Teen Center utility application
Passed 5–0 · unanimousApproved on . Utility Application for City of Freeport and Irrigation Regulations for Freeport Business Complex, Building A, Suite 122 for the Freeport Library Teen Center.
Underground Utilities Locator Services contract renewal
Passed 5–0 · unanimousApproved on . First Option to Renew Contract No. 24-10 with Southland Utility Services, Inc. for Underground Utilities Locator Services.
Wildstar broadband update
Discussion update. Commissioner Curry questioned contract performance and milestone compliance. Wildstar proposal to shift towers from south to north Walton discussed. Board recommended continuing current contract until Wildstar formally requests modification.
Parks4 items
Eastern Lake Regional Beach Access
Tabled 4–1 · split. Motion to table the item, then motion to permanently prohibit vending on the Eastern Lake property both passed. The board discussed mechanisms to protect coastal dune lakes and directed Attorney Adkinson to bring back a draft requiring a supermajority to develop regional beach accesses on coastal dune lakes.
Morrison Springs Park vehicle admission fee collection
Passed 5–0 · unanimousApproved. Motion to collect the $4 per-vehicle admission fee effective March 1, 2026, through October 1, 2026.
- $4 per vehicle · Admission fee for Morrison Springs Park
Beach nourishment update
Discussion. Beach survey being completed. County to identify plan and present to U.S. Army Corps of Engineers for construction approvals from beachfront property owners.
Rescue tubes update
Discussion. More than half of supplies anticipated to arrive February 2026. Tubes to be placed at neighborhood beach accesses.
Other9 items
Library Youth AstroNet commitment letter
Passed 5–0 · unanimousApproved on . Library Director authorized to sign Youth AstroNet commitment letter for participation in science education research program.
supporting federal, state, and local law enforcement including ICE
Passed 5–0 · unanimousAdopted. 2026-05 affirming support for federal, state, and local law enforcement, including Immigration and Customs Enforcement (ICE).
Agriculture Center project
Passed 5–0 · unanimousBoard granted request to proceed with public private partnership process. Farm Bureau has earmarked $40,000 towards project. Motion to allocate $1,000,000 from beach chair vending services revenue failed 2-3. Board directed Attorney Adkinson to advertise for proposals under Section 255.065, Florida Statutes for public private partnership.
- $40,000 · Farm Bureau earmarked amount for Agriculture Center project
- $1,000,000 · Proposed allocation from beach chair vending services revenue (failed motion)
Joint BCC/TDC meeting dates approval
Passed 5–0 · unanimousApproved. Proposed joint meeting dates of March 17, 2026, May 5, 2026, and August 18, 2026 were approved.
Federal Lobbying Services RFQ
Passed 5–0 · unanimousApproved. Request approval to advertise a Request For Qualifications (RFQ) 26-07 for Federal Lobbying services.
Engineering Department Quarterly Report
Passed 5–0 · unanimousApproved. Report for October through December 2025 was accepted.
Scrivener's error amendment
Passed 5–0 · unanimousApproved. Request to schedule to consider amending Walton County Code Chapter 20 (Traffic and Motor Vehicles) to correct scrivener's error in Section 20.35.
Volunteer policy approval
Passed 5–0 · unanimousApproved. Adult volunteer release agreement and waiver approved.
Legislation update (SB840, SB180, HB1465)
Discussion. SB840 (2026) would address issues from SB180 (2025). SB218 and HB217 exempt panhandle from SB180 provisions. Attorney Adkinson noted mobility fee could be reintroduced if bills pass.
Coming up
- on Inlet Beach Neighborhood Plan scrivener's error amendment · February 26, 2026
- Public on budgetary impact of potential legislative items · March 10, 2026
- Joint BCC/TDC meeting · March 17, 2026
- Joint BCC/TDC meeting · May 5, 2026